top of page

UK railways ‘Access for All’ audit

  • Writer: Julian Vaughan
    Julian Vaughan
  • Sep 10, 2024
  • 6 min read

This is a blog covering the status of the UK railway stations provided with ‘Access for All’ (AfA) funding to provide step-free access. The ‘Access for All’ funding programme aims to provide an accessible route onto and between railway station platforms and was launched in 2006.

Since its launch, step-free routes have been provided at approximately 200 stations. It is often quoted that more than 75% of rail journeys are now through stations with step-free access. I view this as misleading as by definition this figure includes non-disabled people and makes no reference to the thousands of railway platforms across the UK that remain ‘no-go’ areas for disabled people.

The information below is divided into three sections.

  1. Stations awarded AfA funding in 2014 for Control Period 5 (2014-2019).

  2. The 27 stations awarded AfA funding in 2014, but deferred as a result of the ‘Hendy Report’ to Control Period 6.

  3. Stations awarded AfA funding in 2019 for Control Period 6 (2019-2024)

The results make for grim reading, and some stations will be waiting for well over a decade after their original funding was agreed. Read more about these stations here: http://julianvaughan.blog/2024/08/09/a-decade-of-step-free-delay/

Any errors are mine alone and I do regard the below as a ‘live’ document. Please feel free to get in touch with any corrections.

You are welcome to email me at: ukrailaccessnetwork@gmail.com

I have linked to sources where available and I provide further resources and further reading at the bottom of this post. Completed projects are highlighted in green.

Regarding the stations awarded funding in 2019 for Control Period 6. I understand that following a ‘deep dive’ review into ‘AfA’ projects by the Department for Transport, the deadline for unfinished stations has been extended from 2024 to March 2026.

There is much discussion about the affordability of providing an accessible rail network. I discuss this in this blog: http://julianvaughan.blog/2024/07/16/can-we-afford-not-to-have-an-accessible-railway/

On to the data, starting with the stations awarded funding in 2014.

How are stations awarded ‘Access for All’ funding in 2014 progressing?

Station

Completion Status and Comments

Teddington

Works due to start September 2023 and finish Spring 2024.

Crawley

Complete.

Palmers Green

Due for completion mid 2024

Coulsdon South

Complete.

Shortlands

Due for completion in Spring 2025.

Plumstead

Complete March 2024 – National Rail Enquiries Map is out of date.

Selhurst

Complete.

Carshalton

Complete August 2019.

Canterbury East

Complete.

Bexley

Lifts are open, although the National Rail Map shows no lifts at the station.

Ewell West

Complete.

Alexandra Palace

Due for completion by Spring 2025.

Tring

Complete in 2020 – cost £5.8m.

Stetchford

Complete, but incorrect information on the National Rail Map.Notified in October 24 and January 25

Meols

Complete 2020.

Mills Hill

Complete 2020.

Torquay

Status Unknown.

Totnes

Complete.

Scunthorpe

Complete although lifts only open during staffed hours – therefore should be classed as a B2 station rather than a Category A station. There are 5 W/B trains towards Doncaster after 20.00 when the station staffing is withdrawn.

Headingley

Completed in May 2019, although the national Rail Enquiries map still does not show the lifts at the station.

Taffs Well

Lifts due to be completed imminently.

Treherbert

Status Unknown

How are stations awarded ‘Access for All’ funding in 2014, but then deferred to Control Period 6 (2019-2024) progressing?

As of Sep 2023, work is due to start Spring 2024.

TRAIN OPERATING COMPANY

Completion Date

Comments

ALFRETON

East Midlands Railway

At March 2023 – Due Spring/Summer 2024

TOC emailed for comment, no reply

BARNE

S

South Western Railway

Due early 2024, delayed to end of 2024.

Cost £5.7 million

BARRY (TOWN

)

Transport for Wales

Opened July 2022


BATTERSEA PARK

Southern

No firm date for completion – estimate end of 2026.

As of Sep 23, cost estimate £20 million – £4m from AfA, the rest from developers’ contributions.

CATHAYS

Transport for Wales

Lifts currently being built, estimated completion early 2025


CHATHAM

Southeastern

Opened September 2022

Cost £5.8 million

GARFORTH

Northern

Lifts due to open August 2024.

Cost £6 million‘Beacon’ Bridge – no further news re completion.

GRAYS

c2c

Work due to start Jan 2024 and take 12 months.

No ORR station categorisation.

HITHER GREEN

Southeastern

No information on completion

3.3m passengers annually.

LIVERPOOL CENTRAL

Merseyrail

Lifts opened


LLANELLI

Transport for Wales

Lifts currently being built


LUTON

Thameslink

As of Sep 2023, work due to start Spring 2024.


MARKET HARBOROUGH

East Midlands Railway

Lifts opened

National Rail Enquiries station map (or description) does not indicate the station has lifts.

NORTHALLERTON

Trans Pennine Express

Opened March 2022


PECKHAM RYE

Southern

Work due to start 2026

PETTS WOOD

Southeastern

Lifts opened early 2024

Cost £10.79m

QUEEN’S PARK

London Underground

Delayed – No clear data available


SEVEN SISTERS

London Overground

No data available


SOUTHEND EAST

c2c

No data available


ST MARY CRAY

Southeastern

Lifts opened February 2022


STREATHAM

Southern

Lifts opened December 2023


THEALE

Great Western Railway

Work due to be completed either Winter 23/24 or Spring 2024 depending on source.

Cost £9.5m

TREFFOREST

Transport for Wales

No data available

Currently classed as B2 station as per ORR classification.

WALTON-on-THAMES

South Western Railway

Lifts Open

Classed as B2 station due to steep gradient of ramp to platform 1.

WARWICK

Chiltern

Work currently paused

Work paused due to finding foundations of original station.

WESTON-SUPER-MARE

Great Western Railway

Plans submitted in June 2023


WORCESTER SHRUB HILL

West Midlands Railway

Work is due to be completed by the end of 2023. No lifts working at present.

Currently classified as a B3 station

How are stations awarded ‘Access for All’ funding in 2019 (Control Period 6) progressing?

S

Train Operating Company

Progress

C

ABERGAVENNY

Transport for Wales

Due to complete Early 2025

NR press release.

ANNIESLAND

ScotRail

Due to complete Sep 2024

email from ScotRail.Update now open October 2024.

BEACONSFIELD

Chiltern

No Data found


BEESTON

East Midlands Railway

Due to complete Autumn 2024

Added March 2020 Budget

BIGGLESWADE

Great Northern

Originally due to be complete in late 2022. Now no completion date.*Update* Now due for completion December 2025.


BIRKENHEAD PARK


Works complete


BRIDLINGTON


Works complete


BROAD GREEN

Northern

Closed for refurb until Winter 2024


CAERPHILLY

Transport for Wales

No Data found


CATFORD


Works complete


CHALKWELL

c2c

Delayed to 2026

CHORLEY

Northern

Due to be completed in August 2024 – no update found in Jan 2025.


CRICKLEWOOD

Thameslink

In development – delayed in March 2024

Source: NR Access for All Map

CROWBOROUGH


Works complete £4.7m


CROY


Works complete


CWMBRAN

Transport for Wales

Due to be completde by late Summer/ end of Autumn 2024 depending on which press release you read.

DAISY HILL

Northern

Due to complete Dec 2024/April 2025

DUMFRIES


Works complete


EAGLESCLIFFE

Northern

Due to complete Autumn 2025

Added March 2020 Budget

EAST GRINSTEAD

Southern

Works Complete Sep 22 £4.5m

Added March 2020 Budget

ERIDGE


Works Complete

Added March 2020 Budget

FLINT

Transport for Wales

Due to complete by end of 2024

FLITWICK

Thameslink

No firm date for completion

Added March 2020 Budget

HACKNEY DOWNS

London Overground

As of Aug 2024 work not started

HANDFORTH

Northern

Due to be complete early 2026

HERNE BAY

Southeastern

Due to complete Winter 2024

HERTFORD NORTH

Great Northern

In development – due Jan 2025

HILLSIDE


Works complete


HUNT’S CROSS


Works complete


IRLAM

Northern

Due to complete Jan 2025/May 2025

ISLEWORTH


Works complete


JOHNSTONE


Works complete


KINGS LANGLEY

London Northwestern Railway

3 Lifts ‘in development’ – no data


LEATHERHEAD

Southern

Due to complete Spring 2025 £6.2m

LUDLOW

Transport for Wales

Due to complete Sep 2024

MENSTON

Northern

Due to complete Feb 2025

MILL HILL BROADWAY

Thameslink

No work started as of March 2024.

NEWTOWN

Transport for Wales

Due to be completed by Autumn 2024/ end of 2024.

PORT GLASGOW


Works Complete

Finished Dec 2023

RETFORD


Works complete


TransPennine Express

Due to complete June 2023

Awaiting update from Network Rail: email sent 10/09/2024*Update 19th September – lifts opened on Monday 16th September.

SHOTTON

Transport for Wales

No data available. Not step-free as per National Rail Accessibility Map 15.01.2025.

Awaiting update from Network Rail: email sent 10/09/2024 no update received.

SMETHWICK ROLFE STREET

West Midlands Railway

Work due to be finished July 2022

Awaiting update from Network Rail: email sent 10/09/2024*Update 11th September – the station lifts opened in Sep 2022. The data on the Access Map and NRE website map does not show any lifts. I have raised this with WMR.

ST ERTH

Great Western Railway

Due to complete in Spring 2024. As of 15.01.2024 not completed.

SOUTH CROYDON

Southern

No data

Added March 2020 Budget

ST MICHAELS


Works complete


STONELEIGH

South Western Railway

Due to complete Summer 2024

STOWMARKET

Greater Anglia

Work due to start September 2023 – Modular design

TENBY

Transport for Wales

‘In development’ – no further data

Awaiting update from Network Rail: email sent 10/09/2024

TODMORDEN

Northern

Under Construction


TOOTING

Thameslink

Due to be completed in Autumn 2024/January 2025

Added March 2020 Budget

UDDINGTON


Works complete


WALKDEN

Northern

‘In development’ – no further data.*Update -delayed by historic mineshaft found when doing prep work.

Added March 2020 Budget.

WANDSWORTH TOWN

South Western Railway

‘In development’

Due to start on site in late 2024.

WELLINGTON

West Midlands Railway

‘In development’ – not started as of May 2024.





Julian Vaughan

10th September 2024 – and amended on various dates up to 15th January 2025

Sources and Further Reading:

Starmer, Rail Accessibility and Tanni GT: 1st September 2024 http://julianvaughan.blog/2024/09/01/starmer-rail-accessibility-and-tanni-gt/

Access for All: Nominated stations for Control Period 7 – 310 were nominated, of which 50 were selected:http://julianvaughan.blog/2024/07/17/access-for-all-nominated-stations/

Actions, not words needed on rail accessibility: 30th April 2024 http://julianvaughan.blog/2024/04/30/actions-not-words-needed-on-rail-accessibility/

 
 
 

Recent Posts

See All
Which way now for Rail Accessibility under Labour?

<p>A post on why we should all be concerned about the Labour government&#8217;s commitment to an accessible rail network. Below is a list of the 50 stations selected for &#8216;Access for All&#8217; (

 
 
 

Comments


bottom of page